I & R Division Projects

A listing of Infrastructure and Regulation Division's capital projects and their current status. Click on a project's title for more information.


IR Capital Projects

Resurfacing / Paving (3 Projects)

Roadway Resurfacing

30 of 35 Miles Completed     (86%)
Currently, we have 35 miles programmed into our system to be improved for FY 17. 32 miles to be completed by end of June. As we complete improvements on different sections, the display is updated.
Andy Markunas (843) 915-5160

Road Plan - Dirt Road Paving

4.22 of 27.51 Miles Completed     (15%)
Miles Paved = completed mileage of roads paved during current FY. (4.22 miles completed-paved during FY 17 / 8 miles total programmed for FY 17). Total miles = the sum of completed mileage (this FY) + mileage of projects "under construction" or "ready for construction" + remaining mileage of prior planned / programmed projects. 5.95 miles currently under construction include the following roads -- Simpson Creek Dr Pt 1 and Pt 2, Durham Lane, Murrells Landing Road, Steep Landing Road, Ruby Lane, Cartrette Rd, Dupont Road, Bill Grissett Rd, and Sioux Swamp Rd Part 2. Strawberry Road CTC. 5.65 miles are ready for construction or are in the engineering design process. 11.69 miles of roads have been approved for paving and are in the R/W acquisition process.
Larry Hamilton and David Gilreath (843) 915-5160

Group 4 Sales Tax Dirt Road Paving

8.99 of 27.75 Miles Completed     (32%)
Fourth and final group of dirt road paving projects funded through Ride 2 (Local Option Sales Tax Program). Total mileage of roads to be paved = 27.75 Mileage paved is as of 2/28/2017 -- and does not reflect projects under construction. For more information on project status by roadway please go to: http://www.salestaxfordirtroads.com/Files/Group%20IV%20-%20Overall%20ROW%20Status.pdf
Rob Hamzy 803-996-2900

Road Construction (8 Projects)

Glenns Bay Road Project Status: Behind Schedule

Estimated Completion Dates
Design: September 1, 2013
Permitting: September 1, 2013
RoW Acquisition: TBD
Construction: April 1, 2018
Construction: 60 % Complete
Widening of Glenn's Bay Road from a 2-lane shoulder section to a 3-lane curb and gutter facility with sidewalks on both sides from US 17 Bypass to US 17 Business, a distance of approximately 1.6 miles. The project will also include an interchange at US 17 Bypass and Glenn's Bay Road.
Leah Quattlebaum 803-737-1751

SC 707 Widening Project Status: Behind Schedule

Estimated Completion Dates
Design: May 1, 2013
Permitting: May 1, 2013
RoW Acquisition: TBD
Construction: March 1, 2018
Construction: 60 % Complete
Widening of SC 707 from 2-lane shoulder section to a 5-lane curb and gutter facility with sidewalks from just south of Enterprise Road in Horry County to US Route 17 in Georgetown County, a distance of approximately 9.2 miles. Currently, construction efforts continue on bridges over Collins Creek and Mill Creek. Installation of base course, drainage system, and sidewalk ongoing throughout Phase I, installation of earthwork and drainage system on Phase II.
Leah Quattlebaum 803.737.1751

International Drive Project Status: Behind Schedule

Estimated Completion Dates
Design: November 1, 2013
Permitting: August 1, 2016
RoW Acquisition: August 1, 2016
Construction: April 1, 2018
Construction: 10 % Complete
Pave and widen International Drive between River Oaks Drive and SC Hwy 90.
Andrew Markunas (843) 915-5160

JT Hucks Bridge Replacement Project Status: On Schedule

Estimated Completion Dates
Design: July 1, 2016
Permitting: October 1, 2016
RoW Acquisition: March 1, 2017
Construction: September 1, 2017
Construction: 0 % Complete
Replacement of single span bridge
David Gilreath

Poplar Church Bridge Replacement Project Status: On Schedule

Estimated Completion Dates
Design: July 1, 2016
Permitting: August 1, 2016
RoW Acquisition: January 1, 2017
Construction: September 1, 2017
Construction: 0 % Complete
Replacement of single span bridge.
David Gilreath

Cobblestone Bridge Replacment Project Status: Completed On Schedule

Estimated Completion Dates
Design: July 1, 2016
Permitting: September 1, 2016
RoW Acquisition: October 1, 2016
Construction: February 1, 2017
Replacement of single span bridge.
David Gilreath

Simpson Creek Bridge Replacement Project Status: Completed On Schedule

Estimated Completion Dates
Design: July 1, 2016
Permitting: August 1, 2016
RoW Acquisition: August 1, 2016
Construction: January 1, 2017
Replacement of double span bridge
David Gilreath

Carolina Bays Parkway Extension (SC 31) - SC 544 to SC 707 Project Status: On Schedule

Estimated Completion Dates
Design: May 1, 2013
Permitting: May 1, 2013
RoW Acquisition: May 1, 2013
Construction: March 1, 2018
Construction: 60 % Complete
Construction of the southern extension of Carolina Bays Parkway (SC 31) from SC 544 to SC 707. New six-lane limited-access freeway involves the construction of a new bridge across the Intracoastal Waterway (ICW) and it will extend Carolina Bays Parkway to its new and final southern terminus at SC 707 (near Moss Creek Road).
Leah Quattlebaum (SCDOT) 803-737-1751

Building (5 Projects)

New University Fire Station Project Status: Behind Schedule

Estimated Completion Dates
Property Acquisition: May 1, 2016
Design: July 1, 2016
Permitting: September 1, 2016
Construction: August 1, 2017
Construction: 90 % Complete
Currently under construction.
John Barnhill 843.915.5300

West Precinct Addition Project Status: Completed On Schedule

Estimated Completion Dates
Property Acquisition: January 1, 2000
Design: August 1, 2015
Permitting: February 1, 2016
Construction: February 1, 2017
Adding an addition to the HCPD West Precinct. Contractor has completed project.
John Barnhill 843.915.5300

New Aynor Fire Station Project Status: On Schedule

Estimated Completion Dates
Property Acquisition: January 1, 2000
Design: May 1, 2017
Permitting: July 1, 2017
Construction: August 1, 2018
New Aynor Fire Station at the Jordanville Road site
John Barnhill 843.915.5300

Fire Training Center Project Status: On Schedule

Estimated Completion Dates
Property Acquisition: TBD
Design: TBD
Permitting: TBD
Construction: TBD
New Fire Training Facility. Site and plans TBD
John Barnhill 843.915.5300

Fleet Maintenance Shop Addition Project Status: Completed Behind Schedule

Estimated Completion Dates
Property Acquisition: January 1, 2000
Design: November 1, 2016
Permitting: January 1, 2017
Construction: June 1, 2017
Addition of two service bays to the light duty portion of the Fleet Maintenance Building.
John Barnhill 843.915.5300

Drainage (4 Projects)

Cameron Village Emergency Outfall Project Status: On Schedule

Estimated Completion Dates
Design: February 1, 2017
Permitting: April 1, 2017
Construction: August 1, 2017
Construction: 50 % Complete
Working to construct an emergency outfall to reduce flooding in Cameron Village. DDC study has been completed, now working with GSWSA on the emergency outfall.

Bellegrove Drainage Improvements Project Status: On Schedule

Estimated Completion Dates
Design: March 1, 2017
Permitting: April 1, 2017
Construction: July 1, 2017
Construction: 90 % Complete
Construct additional outfall system along River Oaks Blvd.

Southcreek at Myrtle Beach National Drainage Project Status: On Schedule

Estimated Completion Dates
Design: April 1, 2017
Permitting: June 1, 2017
Construction: August 1, 2017
Improve Drainage System in the National Drive area to reduce flooding.

Bay Road Drainage Improvements Project Status: On Schedule

Estimated Completion Dates
Design: October 1, 2017
Permitting: January 1, 2018
Construction: June 1, 2018
Drainage and Traffic Safety Improvement Project. Goals are to reduce flooding and improve safety by eliminating deep roadside ditches.

Parks (2 Projects)

Ten Oaks Park Project Status: On Schedule

Estimated Completion Dates
Design: January 1, 2017
Permitting: February 1, 2017
Construction: November 1, 2017
Construction: 20 % Complete
Park improvements
John Barnhill 843.915.5300

New Town Park Project Status: On Schedule

Estimated Completion Dates
Design: January 1, 2016
Permitting: February 1, 2017
Construction: December 1, 2017
Construction: 30 % Complete
Park Improvements.
John Barnhill 843.915.5300