This page provides the status and details of RIDE 3 projects. Click a project heading below for more information on that project. Additional information about the RIDE 3 program can be found here.


Profile

Ride III Dashboard

Resurfacing / Paving (5 Projects)

Pave 25 miles of County dirt roads - Group 1

0 of 24.56 Miles Completed     (0%)
GROUP 1 PAVING 24.56 Miles District 7 Copperhead Road 1.64 Pope Martin 0.86 Total 2.50 District 9 Winburn Road 0.84 Tom Dorman 1.81 Suggs Street 1.34 Total 3.99 District 10 Rodney Road 1.54 Hucks Road 1.37 W G Road 1.07 Harvey Road 1.10 Gause Road 1.97 Bay Gully Road 1.71 Daphane Road 0.78 Total 9.54 District 11 Johnson Shortcut 1.69 Grier Dock Road 1.50 Page Road 1.98 John Cannon Road 1.36 Dorchester Road 1.04 Hardwick Loop 0.96 Total 8.53 Estimated budget: $15M
Larry Hamilton (843) 915-5160 Ride3Info@horrycounty.org

Pave 25 miles of County dirt roads - Group 2

0 of 24.46 Miles Completed     (0%)
GROUP 2 PAVING 24.46 Miles District 7 Flossie Road 1.05 Kinlaw Lane 1.02 Total 2.07 District 9 Long Acres Drive 1.10 Dayton Drive 0.77 Wayside Drive 1.29 Hagan Road 0.77 Total 3.93 District 10 McNabb Road 1.53 Fairlane Road 1.97 Neil Branch Road 1.46 Grainger Circle 1.77 Ware Drive 1.59 Memory Lane 1.01 Gateway Drive 0.77 Total 10.10 District 11 Tyler Road 1.74 Bellaire Drive 1.71 Jordan Lake Road 1.33 Baywater Drive 1.24 Sycamore Circle 1.50 Vick Road 0.84 Total 8.36 Estimated budget: $15M
Larry Hamilton (843) 915-5160 Ride3Info@horrycounty.org

Pave 25 miles of county dirt roads - Group 3

0 of 26.11 Miles Completed     (0%)
GROUP 3 PAVING 26.11 Miles District 7 Reba Road 1.76 New Road 0.96 Total 2.72 District 9 Hufford Road 1.01 Sweet Home Drive 1.01 Birchfield Drive 0.80 Olin Road 0.93 Total 3.75 District 10 Macedonia Drive 1.00 Harrelson Road 1.55 New Dawn Lane 1.48 Bedford Road 1.33 Dukes Road 1.45 Booth Road 1.21 Watts Road 0.89 Bonnie Bay Road 1.58 Total 10.49 District 11 Tranquil Road 1.69 Turner Road 1.53 Maplewild Road 1.64 Norris Road 1.44 Firehouse Road 0.85 Rosedale Drive 1.04 Minnick Road 0.96 Total 9.15 Estimated budget: $15M
Larry Hamilton (843) 915-5160 Ride3Info@horrycounty.org

Pave 25 miles of county dirt roads - Group 4

0 of 25.01 Miles Completed     (0%)
GROUP 4 PAVING 25.01 Miles District 7 Tranquil Road 2.46 Total 2.46 District 9 Hewitt Road 0.83 Old Chesterfield Road 0.82 Tarton Drive 0.73 Vera Road 0.68 Mill Swamp Road 0.75 Total 3.81 District 10 Grainger Road 1.41 Southfork Road 1.43 Westmoreland Road 1.22 Old Irish Road 0.87 Grahamville Road 0.79 Strickland Road 1.54 Tansy Road 1.41 Cookes Circle 1.34 Total 10.01 District 11 Sarvis Road 1.82 Hwy. 712 1.64 McCracken Road 1.40 Providence Drive 1.35 Pasture Drive 1.35 Marvin Road 1.17 Total 8.73 Estimated budget: $15M
Larry Hamilton (843) 915-5160 Ride3Info@horrycounty.org

Resurface 100 miles of paved roads

0 of 100 Miles Completed     (0%)
Funding for roadway resurfacing will be distributed between county and municipalities based on locally-maintained paved roadway mileage in each jurisdiction: Horry County - 66.87% Myrtle Beach - 12.90% Conway - 6.70% North Myrtle Beach - 6.53% Surfside Beach - 3.00% Loris - 1.00% Atlantic Beach - 1.00% Briarcliffe Acres - 1.00% Estimated budget: $15M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Road Construction (14 Projects)

U.S. Hwy. 501 Widening from SC Hwy. 31 to SC 544 Project Status: On Schedule

Estimated Completion Dates
Design: TBD
Permitting: TBD
RoW Acquisition: Summer 2019
Construction: Spring 2021
Complete 6-lane widening and signalized intersection improvements on U.S. Hwy. 501, from SC Hwy. 31 to SC 544 interchange. Estimated budget: $41M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Carolina Forest Boulevard Widening Project Status: On Schedule

Estimated Completion Dates
Design: September 2018
Permitting: October 2018
RoW Acquisition: October 2018
Construction: TBD
Complete widening of Carolina Forest Boulevard to River Oaks Drive. Improved road will include a multi-use path, 4-lanes (with turning lanes at intersections) and traffic signals as determined by traffic study during design phase. Estimated budget: $54.7M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Palmetto Pointe Boulevard Extension to SC Hwy. 544 Project Status: On Schedule

Estimated Completion Dates
Design: June 2018
Permitting: June 2018
RoW Acquisition: June 2018
Construction: March 2019
Construct extension of Palmetto Pointe Boulevard to connect to SC Hwy. 544 at the Big Block Road intersection. New road will include 2-lanes and bike/pedestrian facilities such as sidewalks and wider travel lanes. Estimated budget: $7.5M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

SC Hwy. 9 East Widening (Loris) Project Status: On Schedule

Estimated Completion Dates
Design: TBD
Permitting: TBD
RoW Acquisition: Summer 2019
Construction: Fall 2021
Widen SC Hwy. 9 east of Loris, from the end of the existing 4-lane section to intersection of Hwy. 66. Improved road will be expanded to 4-lanes with sidewalks. Estimated budget: $21.7M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

U.S. Hwy. 701 N. Widening (North Conway) Project Status: On Schedule

Estimated Completion Dates
Design: TBD
Permitting: TBD
RoW Acquisition: Winter 2019
Construction: Fall 2022
Widen U.S. Hwy. 701 north of Conway, from SC Hwy. 319 to Hwy. 22. Improved road will feature 5-lanes, including a center turn-lane and installation of bike/pedestrian facilities such as sidewalks and wider travel lanes. Estimated budget: $65.1M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Fred Nash Boulevard connection to Harrelson Boulevard- Myrtle Beach Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Summer 2019
Construction: Fall 2021
Construct new 3-lane road, including a center turn-lane, to extend Fred Nash Boulevard around the end of the airport runway (MYR) to provide a direct connection to Harrelson Boulevard. The project includes bicycle facilities. Estimated budget: $19.3M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

U.S. 17 Business Intersection Improvements - Garden City Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Spring 2019
Construction: Spring 2021
Improve capacity and safety at the following three intersections in Garden City (intersection widening, turn lane extensions, and other operational improvements): 1.) U.S. 17 Business @ Inlet Square Mall/Mt. Gilead Road 2.) U.S. 17 Business @ Atlantic Avenue 3.) U.S. 17 Business @ Garden City Connector/Pine Avenue Estimated budget: $19.8M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Forestbrook Road Widening Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Winter 2019
Construction: Spring 2023
Widen Forestbrook Road, between U.S. Hwy 501 and Dick Pond Road. Improvements will feature 5-lanes including a center turn-lane and the installation of bike/pedestrian facilities such as sidewalks and wider travel lanes. Estimated budget: $89.1M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

U.S. Hwy. 501 Realignment from Broadway Street to 7th Avenue North Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Winter 2019
Construction: Spring 2022
Realign U.S. Hwy. 501 at Broadway Street intersection to connect to 7th Avenue North at Oak Street in the City of Myrtle Beach (new alignment). Install sidewalks and intersection improvements on 7th Avenue North, between Oak Street and North Kings Highway. Estimated budget: $13.9M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

U.S. Hwy. 701 Widening - North of Loris Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Summer 2019
Construction: Fall 2021
Widen U.S. Hwy. 701 north of Loris, from end of existing 3-lane section (Dogwood Street) to SC Hwy. 9 interchange. Improved road will include turning lanes and installation of bike/pedestrian facilities such as sidewalks and wider turn lanes. Estimated budget: $7.5M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Conway Perimeter Road Phase II Project Status: On Schedule

Estimated Completion Dates
Design: Spring 2018
Permitting: TBD
RoW Acquisition: Summer 2019
Construction: Fall 2021
Construct new road with multi-use path from U.S. Hwy. 378 (at El Bethel Road) to U.S. Hwy. 701 south. The new road will feature 4-lanes with median and turning lanes at the intersection. Estimated budget: $18.4M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

Southern Evacuation Lifeline (SELL)- Environmental Studies and Right-of-Way Project Status: On Schedule

Estimated Completion Dates
Design: TBD
Permitting: TBD
RoW Acquisition: TBD
Construction: TBD
Funding to complete the final environmental impact studies required to obtain Record of Decision (ROD) for future roadway. Purchase land for right-of-way of final alignment identified in the Record of Decision. Estimated funding: $25M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

SC Hwy. 31 (Carolina Bays Parkway) Extension to SC/NC State Line Project Status: On Schedule

Estimated Completion Dates
Design: TBD
Permitting: TBD
RoW Acquisition: TBD
Construction: TBD
Final phase of SC Hwy. 31 (Carolina Bays Parkway). Build new limited-access freeway to extend SC Hwy. 31 from SC Hwy. 9 to North Carolina state line. Estimated funding: $125M *Total cost to complete SC 31 Extension north is estimated at $185M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org

U.S. Hwy. 501 Corridor Improvements Project Status: On Schedule

Estimated Completion Dates
Design: June 2019
Permitting: June 2019
RoW Acquisition: April 2019
Construction: TBD
1.) Extend Postal Way east to Waccamaw Pines Drive and install required intersection improvements and sidewalks (including Postal Way @ Carolina Forest Boulevard/Renee Drive/Oak Heart Road). 2.) Extend Middle Ridge Avenue east (Myrtle Ridge Drive to West Perry Road) - and west (Walmart to Singleton Ridge Road). Estimated budget: $9M
Jason Thompson (843) 915-5160 Ride3Info@horrycounty.org